|
|
RESPONDENT=S MOTION
FOR SUMMARY RELIEF GRANTED
IN PART; APPELLANT=S MOTION FOR SUMMARY RELIEF
DENIED: November 13, 2009
CBCA
938
JAVIS AUTOMATION &
ENGINEERING, INC.,
Appellant,
v.
DEPARTMENT OF THE
INTERIOR,
Respondent.
Crishon D. Jordan, Knightdale, NC,
counsel for Appellant.
Stephen R. Palmer, Office of the
Regional Solicitor, Department of the Interior, Sacramento, CA, counsel for
Respondent.
Before DANIELS (Chairman), GILMORE, and HYATT,
Board Judges.
HYATT, Board
Judge.
This appeal is from a contracting
officer=s decision seeking to recover from appellant, JAVIS
Automation & Engineering, Inc. (JAVIS), the amount of $333,955 in alleged
overpayments made under task orders issued pursuant to a letter contract for
the provision of information technology and geographic information system
services.
JAVIS and respondent, the
Department of the Interior, Bureau of Reclamation (BOR), filed an extensive
joint stipulation of undisputed facts,[1]
followed by the submission of
cross-motions for summary relief.
For the reasons set forth below, we deny JAVIS=s motion and grant the Government=s motion in part.
Findings
of Fact
1. In
September 2001, JAVIS and BOR entered into letter contract no. 01-CS-20-2178,
under which JAVIS was to provide BOR with information technology (IT) and
geographic information system (GIS) services.
The letter contract provided that the definitized contract would be an
indefinite delivery/indefinite quantity (IDIQ) type contract, with work to be
performed as identified in task orders issued by the contracting officer. Task orders could be issued as cost-plus-fixed-fee
(CPFF), time and materials (T&M), or fixed price. The letter contract included Federal
Acquisition Regulation (FAR) clause 52.216-26, permitting payment
of allowable costs before definitization. The letter contract was originally scheduled
to be definitized by December 5, 2001.
Appeal File, Exhibit B.2; SF &&
2-6.
2. On
December 5, 2001, BOR issued the first two task orders for work under the
contract, one (order 01A1202178) for GIS services, and the other (order
01A2202178) for IT services.[2] The funding estimate for the GIS task order
was $800,000. For the IT task order the
funding estimate was $125,000. Each of these
task orders proposed a new definitization date of February 10, 2002, which also
became the target date for definitization of the letter contract. Appeal File, Exhibit B.2; SF && 7-8, 10-11.
3. The
start date for each task order was retroactive to October 1, 2001, and the end
date was September 30, 2002. In
enumerating the categories of services to be purchased, both task orders were
identified as Acost plus fixed fee@ in
several places. The task orders also
provided that final rates and fee would be negotiated and definitized. Appeal
File, Exhibit B.2; SF & 14.
4. The GIS task order set forth labor
categories, estimated hours, and estimated rates for the various labor
categories. Estimated amounts were to
include all direct and indirect costs and fee.
The estimated hours and amounts were to be negotiated at
definitization. Appeal File, Exhibit
B.2; SF &
13.
5. Modification 0001 to the GIS task order
01A1202178, in which BOR exercised the option to extend performance for another
year, through September 30, 2003, was issued on September 30, 2002, effective
September 25, 2002. Modification
0001repeated that the task order was CPFF and further stated A[t]he
estimated hours and amounts for these labor categories are to be negotiated at
the definitization of the Letter Contract.@ Modification 0002 to the GIS task order,
obligating additional funding, was
issued on September 9, 2003.
Modification 0003 was issued on December 18, 2003. This modification exercised an option to
extend performance for six moths, from October 1, 2003, through March 31,
2004. Modification 0004 was issued on
January 30, 2004. Modification 0005
extended the date of completion of the GIS task order to May 28, 2004, and was
issued on April 27, 2004. Modification
0006, issued on August 31, 2004, extended the period of performance from May 28
through August 2, 2004. Appeal File,
Exhibit B.2; SF & 14.
6. IT task order 01A2202178, issued on
December 5, 2001, stated that it was a CPFF task order and that A[f]inal
labor categories, labor rates and estimated hours for performance will be
negotiated at the definitization of the Letter Contract.@ Modification 0001 to the IT task order was
issued on December 13, 2002, effective December 11, 2002, for the purpose of
adding funding to the task. It confirmed
that this was a CPFF task order and stated that A[f]ina1
labor categories, labor rates and estimated hours for performance will be
negotiated at the definitization of the Letter Contract.@ Appeal File, Exhibit B.3; SF &
14.
7. JAVIS commenced performing services under
the letter contract in early October 2001, prior to issuance of the task
orders. By December 18, 2001, JAVIS had
submitted three invoices for payment.
All three invoices billed the work performed under the task orders by
multiplying hours worked by hourly rates.
SF &&
15-16.
8. In a letter dated December 18, 2001, the
BOR contracting officer informed JAVIS that its invoices had been approved and
forwarded for payment. The letter stated
that A[a]ll
costs on these invoices were approved except for Other Direct Costs and the
labor costs for the Administrative Specialist.@ At the same time, the contracting officer
cautioned that A[i]t
is apparent you submitted and [were] paid direct labor rates that include all
indirect costs and profit or fee. We
have not negotiated any of these direct or indirect costs or profit/fee with
JAVIS. We are treating all costs as
provisional pending definitization.@ Appeal File, Exhibit C.2.4; SF &&
17-18.
9. In a letter dated December 31, 2001,
JAVIS responded to BOR=s
contracting officer and contract specialist enclosing proposed cost information
for the two task orders. The proposal
included tables displaying the salary labor rates, fringe, overhead, general
and administrative (G&A) expenses, fees, and the base annual hours for each
labor category. This letter also stated
that the rates used were based on rates evaluated by the Defense Contract Audit
Agency (DCAA). Finally, JAVIS requested
that the GIS task order be converted to a firm-fixed-price basis. SF && 19-20.
10. On January 7, 2002, the DCAA wrote to
JAVIS and approved provisional billing rates for JAVIS=s fiscal
year 2002 (January 1 through December 31, 2002). Appeal File, Exhibit C.2.12; SF &
21.
11. Beginning in February 2002, the parties
made efforts to definitize the letter contract.
In a letter dated February 22, 2002, BOR=s
contracting officer asked JAVIS to submit a cost/price proposal for the basic
contract in accordance with sections B, H, J, and L of the solicitation. The letter noted that a cost/price proposal
previously had been submitted for both the IT and GIS task orders, but added
that the Government required a proposal for the basic contract as well. Appeal File, Exhibit C.2.7; SF && 22-23.
12. In response to the contracting officer=s
request, JAVIS provided its proposal to BOR on March 5, 2002. The proposal included specific fully burdened
hourly labor rates and labor categories.
Appeal File, Exhibits C.2.9, G.5; SF && 22-25.
13. In April 2002, the parties engaged in
discussions in an effort to definitize the contract. The parties considered changing the billing
method to that of a firm-fixed-price contract and submitting bi-weekly invoices
in order to resolve definitization issues.
Appeal File, Exhibit G.6; SF & 25.
14. On June 24, 2002, BOR forwarded the JAVIS
cost proposal to the DCAA for review, advising that the existing task orders
were Aboth
cost plus fixed fee.@ Appeal File, Exhibit G.7; SF &
26.
15. On July 1, 2002, another BOR contracting
officer assigned to this contract wrote to JAVIS with questions regarding the
proposal JAVIS had submitted on March 5, 2002.
In particular, she asked JAVIS to clarify and justify a Afringe
rate@ of
sixteen percent, and requested a rationale for the application of overhead
rates. Appeal File, Exhibit C.2.11; SF & 27.
16. On July 24, 2002, the operations manager for
JAVIS wrote to the contract specialist and the contracting officer enclosing a
definitized cost schedule for the basic contract period and for the first and
second option periods. Appeal File,
Exhibit G.8; SF & 28.
17. Subsequently, BOR contacted JAVIS to seek
reconciliation of perceived inconsistencies that BOR had identified in the
proposal. JAVIS responded with a
corrected proposal. Although BOR evaluated JAVIS=s
cost proposal, the parties never reached agreement as to the proposal and never
definitized the letter contract or the task orders. SF && 29- 31.
18. JAVIS continued to perform services under
the undefinitized letter contract and to bill for those services using the
proposed labor rates. BOR continued to
pay JAVIS=s
invoices, but not all invoices were paid in full. SF && 32-33.
19. On September 24, 2002, JAVIS submitted its
final invoice for the IT task order in the amount of $26,783.92. SF & 34.
20. On September 26, 2002, BOR issued
modification 1 to the letter contract, exercising its one year option to extend
the period of performance from October 1, 2002, to September 30, 2003. Appeal File, Exhibit B.1; SF &
35. On September 30, 2002, BOR issued
modification 0001 to the GIS task order, exercising its one year option to
extend the period of performance from October 1, 2002, to September 30, 2003. Modification 0001 also increased the amount
of the GIS task order from $800,000 to $1,700,000. Appeal File, Exhibit B.2; SF &
36.
21. On December 13, 2002, BOR issued
modification 0001 to the IT task order, amending the task order amount to
$164,086.56 and permitting payment before definitization. Appeal File, Exhibit B.3; SF &
37.
22. BOR paid all amounts that were billed by
JAVIS under the IT task order. SF & 38.
23. In a letter dated January 24, 2003, a new
BOR contracting officer asked JAVIS to submit another cost proposal for
definitization of the letter contract.
Appeal File, Exhibit C.2.8. Once
again, the parties failed to bring their negotiations to a conclusion and
neither the letter contract nor the task orders were ever definitized. SF && 39-40.
24. On September 9, 2003, BOR issued
modification 0002 to the GIS task order, increasing the amount of the task order
by $300,000 from $1,700,000 to $2,000,000.
On December 18, 2003, BOR issued
modification 0003 to the GIS task order to extend services for an additional
six months -- from October 1, 2003, through March 31, 2004. The total amount of the GIS task order was
increased from $2,000,000 to $2,865,000.
On April 27, 2004, BOR issued modification 0005 to the GIS task order,
extending the period of performance at no additional cost from March 31 to May
28, 2004. Appeal File, Exhibit B.2; SF &&
41-43.
25. On August 6, 2004, JAVIS submitted its
final invoice for the GIS task order in the amount of $169,263.24, of which
$28,351.45 was paid, leaving a balance of $140,911.79. SF & 44.
26. On August 31, 2004, the Government
retroactively issued modification 0006
to the GIS task order, extending the period of performance from May 28,
2004 to August 2, 2004, at no additional cost to either party. The modification stated: AEstimated
management hours of 250 per year at $80 per hour, total $20,000 for this line
item. This estimated hourly rate
includes all indirect costs and fee. The
estimated hourly rate and number of hours for this management category are to
be negotiated at the definitization of the Letter Contract.@ Appeal File, Exhibit B.2; SF &
45.
27. JAVIS provided services under the GIS task
order through August 2004. SF &
46.
28. Completion of performance under the IT task
order occurred in September 2002, while it remained undefinitized. In a September 2, 2003 letter, the
contracting officer notified JAVIS of performance issues requiring further
action, including cooperating with DCAA regarding an audit of JAVIS=s
rates. Appeal File, Exhibit G.l2; SF &
47.
29. As of the conclusion of the letter
contract, JAVIS had performed all work satisfactorily for BOR under the IT task
order; however, the letter contract remained undefinitized. The period of performance under the GIS task
order ended in August 2004. SF &
48.
30. On September 14, 2005, JAVIS received an
electronic mail message from DCAA acknowledging receipt of time and materials
rates that it had requested, and requesting JAVIS to forward the allowable time
and material rates for the undefinitized letter contract. The auditor also inquired why the contract
was being billed by JAVIS as a time and
materials effort when the task orders specified a CPFF contract. Appeal File, Exhibit C.2.15; SF &
49.
31. With
respect to the DCAA communication, JAVIS=s president and CEO stated in an affidavit
that:
In response to the September 14, 2005 request from
DCAA, JAVIS discussed the billing of the Letter Contract as T&M with Eileen
P. CiCi, Auditor with the DCAA and Evelyn Yamamoto, Contracting Officer with
the BOR. JAVIS understood that agreement
was reached as to the billing of the Letter Contract as T&M. The Indirect Rate Letter included fiscal
indirect cost rates which were consistent with JAVIS= understanding of the Letter Contract=s billing as T&M and the exit briefing discussion
between JAVIS, Eileen P. CiCi, Auditor with the DCAA, and Esther M. Fischer,
Supervisory Auditor with the DCAA. JAVIS
signed the Indirect Rate Letter in agreement with the DCAA and returned it the
next day.
Affidavit
of John Long, Sr. (Nov. 12, 2008) & 11.
32. On October 28, 2005, DCAA issued an
indirect rate letter setting forth the agreed upon final indirect cost rates
established by the DCAA auditor in accordance with FAR 42.705-2(b)(2)(ii) and
Department of Defense FAR Supplement 242.705-2(b )(2)(ii). The rates were applicable to JAVIS=s
fiscal years ending December 31, 2001, and December 31, 2002. JAVIS=s president signed the
letter, accepting the indirect cost rates as final. Appeal File, Exhibit
C.2.16; SF &&
50-51.
33. The indirect rate letter directed JAVIS to
submit adjustment or final vouchers for all flexibly priced contracts. Appeal File, Exhibit C.2.16; SF &
52.
34. From November 2005 through April 2007,
JAVIS sought payment of its final invoices and vouchers on the undefinitized
letter contract. During this time
period, BOR and JAVIS tried to negotiate the definitization amount but could
not reach an agreement. BOR questioned
the final voucher amounts because the rates had not been definitized. SF && 53-54.
35. JAVIS sent a letter, dated July 19, 2006,
to the contracting officer, following up on a meeting held on July 18, 2006, to
discuss final vouchers. In the letter,
JAVIS contended that final contract closeout costs should be determined using
its time and materials rates. JAVIS also
asserted that it had used DCAA=s audited rates for JAVIS=s
fiscal years 2001 and 2002 to bill for the remainder of the contract term and
took the position that the contract should be closed out using those approved
rates. SF &&
55-56.
36. After this correspondence, the parties
still failed to reach any agreement on contract closeout costs. SF & 57.
37. On January 18, 2007, DCAA unilaterally issued a supplemental
memorandum modifying its earlier audit report to correct the contract type from
T&M to CPFF. Appeal File, Exhibit
G.15; SF &
58.
38. After further correspondence, the parties
were still unable to reach an agreement on the amount that should be paid to
definitize and close out the undefinitized letter contract. SF & 59.
39. On August 10, 2007, the contracting officer
issued a decision, providing a
unilateral closeout of task orders 01A1202178 and 01A2202178. The letter stated that it was a final
decision with respect to Aoverpayments
on these task orders.@ The letter also stated that review of all documents and the audit reports
made Aclear
that each of the task orders issued under this IDIQ contract were CPFF and not
T&M.@ Appeal File, Exhibit A; SF &&
60-61.
40. In this letter, the contracting officer
unilaterally closed the letter contract and task orders. With respect to the IT task order, the
contracting officer stated that this order was Abeing
definitized in the amount of $164,086.56, which has been paid in full, all work
performed was acceptable.@ As to the GIS task order, the contracting
officer stated that the DCAA audit issued in January 2007 reflected an
overpayment of $183,277 for fiscal years 2001 and 2002, and an overpayment of
$150,678 for JAVIS=s fiscal
years 2003 and 2004. With respect to
JAVIS=s
fiscal years 2003 and 2004, the contracting officer adopted DCAA=s
recommendation to apply a twenty percent decrement to direct and indirect
costs.[3] The contracting officer then unilaterally
modified the GIS task order to decrease the amount paid by BOR to JAVIS by
$333,955 and demanded that JAVIS refund that amount to BOR. Appeal File, Exhibit A; SF &&
62-66.
41. JAVIS timely submitted a notice of appeal
from the contracting officer=s final decision to the
Civilian Board of Contract Appeals. SF & 67.
42. With respect to the Government=s
understanding of the nature of the task orders and its intentions concerning
pricing, BOR has submitted the affidavit of its contract specialist, who states
that:
The
Letter Contract . . . contains FAR Clause 52.216-26[,] titled APayment
of Allowable Costs Before Definitization[,]@ which states that Athe
Contractor may submit to an authorized representative of the Contracting
Officer, in such form and reasonable detail as the representative may require,
an invoice or voucher supported by a statement of the claimed allowable
expenses incurred by the Contractor in performance of this contract.@ The clause further explains that allowable
costs are those such as supplies/services purchased directly for the contract
and associated financial payments to subcontractors, materials, direct labor,
direct travel, other direct in-house costs, and allowable/allocable indirect costs. Similarly, FAR Clause 52.232-7, titled APayments
under Time-and-Material or Labor-Hour contracts,@
which is also part of the letter contract, states Athe
Government will pay the contractor as follows upon the submission of vouchers
approved by the Contracting Officer or authorized representative by multiplying
the appropriate hourly rate by the number of direct labor hours performed. The hourly rates shall include wages,
indirect costs, general and administrative expense, and profit.@ As the two [types of] contracts are invoiced
in a similar fashion, the fact that the Government accepted invoices from JAVIS
based on hours worked multiplied by hourly rates did not constitute treatment
of the contract as T&M.
Affidavit of Brenda Davis (Dec. 11,
2008) & 2
(Davis Affidavit).
Discussion
Both
BOR and JAVIS have filed motions for summary relief with respect to the proper
interpretation of the terms of the letter contract and the two task orders
issued under it. BOR contends that the
task orders were clearly intended to be, and were treated by the Government as,
CPFF contracts. JAVIS maintains that the
actions of the parties during performance demonstrates that the contracts were
performed as, and paid as, T&M contracts, and thus its interpretation
should prevail. Further, JAVIS contends
that BOR breached its obligation under FAR 52.216-25(c) (Contract
Definitization) to establish a reasonable unilateral contract price
determination upon failing to achieve a mutually agreed upon price
definitization.
Applicable Legal Standards
Summary relief
is properly granted when there is no genuine issue of material fact and the
moving party is clearly entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 247 (1986); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986);
US Ecology, Inc. v. United States, 245 F.3d 1352, 1355 (Fed. Cir. 2001);
Olympus Corp. v. United States, 98 F.3d 1314, 1316 (Fed. Cir. 1996). In resolving summary relief motions, a fact
is considered to be material if it will affect our decision and an issue is
genuine if enough evidence exists such that the fact could reasonably be
decided in favor of the non‑movant at a hearing. John A. Glasure v. General Services
Administration, GSBCA 16046, 03‑2 BCA &
32,284, at 159,746 (citing Celotex Corp.; Matsushita Electric
Industrial Co. v. Zenith Radio Corp., 475 U.S. 574 (1986)). The moving party bears the burden of
establishing the absence of any genuine issue of material fact. Mingus Constructors, Inc. v. United States,
812 F.2d 1387, 1390 (Fed. Cir. 1987).
The nonmoving party is then required to Ago
beyond the pleadings and . . . designate >specific
facts showing that there is a genuine issue for trial.=@ Celotex
Corp., 477 U.S. at 324. In
considering summary relief, the tribunal will not make credibility
determinations or weigh conflicting evidence.
Anderson, 477 U.S. at 249; accord Acquest Government
Holdings U.S. Geological, LLC v. General Services Administration, CBCA 439,
07-1 BCA & 33,576.
When both parties move for summary relief, each party=s motion must be evaluated on its own merits and all
reasonable inferences must be resolved against the party whose motion is under
consideration. Anderson, 477 U.S.
at 248; First Commerce Corp. v. United States, 335 F.3d 1373, 1379 (Fed.
Cir. 2003); DeMarini Sports, Inc. v. Worth, Inc., 239 F.3d 1314, 1322
(Fed. Cir. 2001). The fact that the
parties have cross‑moved for summary relief does not compel a grant of
one of the motions; each motion must be independently assessed on its own
merit. California v. United States,
271 F.3d 1377, 1380 (Fed. Cir. 2001). In
this case, the facts pertinent to determining the nature of the task orders are
largely undisputed.
The issue raised by both parties in their motions is
one of contract interpretation, which is a legal question that is often
amenable to summary disposition. Varilease
Technology Group, Inc. v. United States, 289 F.3d 795, 798 (Fed Cir. 2002)
(citing Textron Defense Systems v. Widnall, 143 F.3d 1465, 1468 (Fed.
Cir. 1998)). The determination of a
contract type is also a matter of law, and the tribunal is not bound by the
label attached to it by the parties. Maintenance
Engineers v. United States, 749 F.2d 724, 726 n.3 (Fed. Cir. 1984);
Mason v. United States, 615 F.2d 1343, 1346 (Ct. Cl. 1980).
The Parties=
Positions
BOR=s argument in support of its motion is
straightforward. BOR asserts that the
two task orders contain express unambiguous statements that the work to be
performed by JAVIS would be paid for on a cost plus fixed fee basis. The task orders set forth various labor
categories, estimated hours, and estimated rates, and also stated that
estimated amounts were to include all direct and indirect costs and fee. Final hours and rates were to be negotiated
at definitization. Construing the
agreements in context and giving full import to all provisions of the
contracts, it follows as a matter of law that the task orders created CPFF
contracts.
JAVIS, for its part, acknowledges that the task orders
state that the work was to be performed and compensated on a CPFF basis, but
nonetheless maintains that other provisions in the task orders, such as the
enumeration of labor categories and estimates of costs of labor categories, are
suggestive of a time and materials arrangement and thus create an ambiguity. It further contends that since the Government
paid appellant=s invoices, which used T&M rates proposed by
JAVIS, BOR effectively created a new implied-in-fact contract under which the
work was performed on a T&M basis.
Finally, JAVIS asserts that the contracting officer=s final decision was issued improperly.
Propriety of Contracting Officer=s Decision
We start with JAVIS=s
contentions concerning the validity of the contracting officer=s decision.
JAVIS posits that the contracting officer failed to follow applicable
regulatory procedures in issuing the final decision with respect to the
closeout of the contract and unilateral determination of the final price or
fee. In support of this assertion, JAVIS
cites FAR 52.216-25(c), which provides that:
If agreement on a definitive contract to supersede
this letter contract is not reached by the target date . . . or within any
extension of [the target date] granted by the Contracting Officer, the
Contracting Officer may, with the approval of the head of the contracting
activity, determine a reasonable price or fee in accordance with subpart 15.4
and part 31 of the FAR, subject to Contractor appeal as provided in the
Disputes clause.
48 CFR
52.216-25(c) (2001). JAVIS contends that
there is no evidence on the face of the decision to show that the contracting
officer=s final decision, which unilaterally determined a Areasonable price,@ was
issued with the requisite approval of the head of the contracting activity and
that the final decision was therefore defective.
In response,
BOR submitted a statement by the contract specialist to the effect that all
appropriate approvals were obtained and the contracting officer was authorized
to issue the decision establishing a definitized price and asserting the
Government=s claim for
refund. Davis Affidavit & 3. JAVIS did
not rebut this evidence. Even if it had,
however, the regulation appellant relies upon is not one that confers a benefit
upon the contractor. Rather, it is the
type of internal regulation that is designed for the agency=s benefit. When
the primary intended beneficiary of a regulation is the Government, a private
party cannot complain about the Government's failure to comply with that
regulation, even if that party derives some incidental benefit from compliance
with it. See, e.g., Freightliner
Corp. v. Caldera, 225 F.3d 1361, 1365 (Fed. Cir. 2000); Cessna Aircraft
Co. v. Dalton, 126 F.3d 1442, 1451-52 (Fed. Cir. 1997); Rough Diamond
Co. v. United States, 351 F.2d 636, 640-42 (Ct. Cl. 1965); Charitable Bingo
Associates, Inc., ASBCA 53249, et al., 05-1 BCA & 32,863.
Proper Interpretation of Contract Language
Although BOR maintains the contract is unambiguous and
clear on its face, appellant disagrees.
Appellant argues that regardless of what the task orders stated, the
conduct of the parties during performance supports its position that the task
orders were actually treated as and became T&M contracts. Appellant points to the fact that the
Government paid its invoices, which were derived by multiplying hours worked by
hourly rates. This, JAVIS contends,
supports its position that the parties agreed to calculate costs using T&M
rates and profit.
Under a T&M contract, the Government acquires
services on the basis of Adirect labor hours at specified fixed hourly rates
that include wages, overhead, general and administrative expenses, and profit.@ FAR 16.601(a);
Resource Consultants, Inc., ASBCA 29710, 86‑2 BCA & 18,916, at 95,403.
A CPFF contract is a cost-reimbursement contract wherein the Government
pays the contractor=s allowable incurred costs to the extent prescribed in
the contract, plus a negotiated fee that ordinarily is fixed at the inception
of the contract. FAR 16.301-3,
.306. Both types of contract contain a
ceiling amount, or limitation on costs incurred, which the contractor exceeds
at its own risk.
The costs that are considered in negotiating fixed
labor rates for a T&M contract are not dissimilar from those that are
compensable under a CPFF contract. The
fact that JAVIS computed its invoices using hourly rates and specific labor
categories was, therefore, not enough to put the Government on notice that
JAVIS interpreted the task orders to be T&M, rather than CPFF, contracts,
or to create a course of conduct reflecting BOR=s
agreement with or adoption of JAVIS=s
interpretation. Nor does payment of
invoices constitute a ratification of JAVIS=s
view.
As respondent notes, in countering appellant=s argument, the letter contract contained FAR clauses
52.216-26 (APayment of Allowable Costs Before Definitization@) and 52.232-7 (APayments
under Time-and-Materials or Labor-Hour Contracts@). Clause 52.216-26 permits the contractor to
submit to the Government an invoice or voucher supported by a statement of the
claimed allowable costs incurred by the contractor in performing. The clause defines allowable costs as
supplies and services purchased directly for the contract and associated
financial payments to subcontractors, materials, direct labor, direct travel,
other direct in-house costs, and allowable/allocable indirect costs. Clause 52.232-7 provides that the Government
will pay the contractor upon the submission of vouchers reflecting an
appropriate hourly rate multiplied by the number of direct labor hours
performed. The clause further states
that the hourly rates shall include wages, indirect costs, general and
administrative expenses, and profit.
Thus, similar information is requested for both types of contracts.
In addition, BOR has provided the affidavit of the contract
specialist assigned to this contract, who stated that A[a]s the two [contract types] are invoiced in a
similar fashion, the fact that the Government accepted invoices from JAVIS
based on hours worked multiplied by hourly rates did not constitute treatment
of the contract as T & M.@ Finding 41.
The task orders= instructions to the contractor on invoicing stated
that estimated hours were to include Aall
direct and indirect costs and fee.@ BOR points out that under the FAR an
appropriate instruction for a T&M effort would be to include Afully burdened@ rates
and a separate amount for profit. This
is reflected in paragraph H.4 of the letter contract. In BOR=s view,
the task orders thus clearly provided for JAVIS to track and invoice costs for
a CPFF contract.
We agree with BOR=s
position. The Government never agreed
through its conduct, either expressly or by implication, that the task orders
were to be priced on a T&M basis.
Regardless of what JAVIS intended by submitting its vouchers, the
Government consistently informed JAVIS that payments were provisional and
subject to audit. The Government
undertook to have the invoices audited.
There was never any concession on the part of the Government that JAVIS=s rates were acceptable and would be adopted under a
T&M format.[4] The record consistently reflects that BOR
wanted to audit the proposals to determine what costs were properly allowable
and allocable to the task orders, and then to attempt to definitize the task
orders. The parties never managed to
complete this process, however.
The dispute presented by the parties is indeed one of
contract interpretation, which begins Awith the
language of the written agreement.@ NVT Technologies, Inc. v. United States,
370 F.3d 1153, 1159 (Fed. Cir. 2004).
The plain and unambiguous meaning of the written agreement controls,
with reasonable meaning given to all of its parts. Hercules Inc. v. United States, 292
F.3d 1378, 1380‑81 (Fed. Cir. 2002).
It is not the subjective intent of any one party that is controlling. Firestone Tire & Rubber Co. v. United
States, 444 F.2d 547, 551 (Ct. Cl. 1971).
The fact that appellant regularly invoiced the Government
using what JAVIS considered to be T&M rates, and was paid on a provisional
basis, did not serve to transform the task order from a CPFF to a T&M
contract. This practice was contrary to
BOR=s invoicing instructions. BOR requested a DCAA audit to determine the
accuracy of the provisional rates, and once it obtained a report, stopped
paying on JAVIS=s GIS task order
invoices. The record supports the
Government=s position that it always understood the task orders
to be CPFF contracts. See Dawkins
General Contractors & Supply, Inc., ASBCA 48535, 03‑2 BCA & 32,305.
JAVIS also argues that the failure to definitize,
together with BOR=s payment of its invoices, served to create an
implied-in-fact T&M contract for the task order services. As respondent points out, this argument is
readily disposed of. An Aexpress contract precludes the existence of an implied
contract dealing with the same subject, unless the implied contract is entirely
unrelated to the express contract.@ Atlas Corp. v. United States, 895 F.2d
745, 754‑55 (Fed. Cir. 1990); see also Trauma Service Group v. United
States, 104 F.3d 1321, 1326 (Fed. Cir. 1997); ITT Federal Support
Services, Inc. v. United States, 531 F.2d 522, 528 n.12 (Ct. Cl. 1976); Todd
Pacific Shipyards Corp., ASBCA 55126, 08-2 BCA & 33,891. The
matters raised in this appeal -- the type of contract and the proper pricing of
the services supplied by appellant -- are covered by the express letter
contract and task orders issued by BOR.
The Aimplied-in-fact@
contract that JAVIS believes was created covers precisely the same subject
matter as the express contracts it already held with BOR.
Finally, JAVIS asserts that BOR=s decision not to claim a refund under the IT task
order, which JAVIS states was also invoiced on a T&M basis, supports its
position that BOR was in agreement with JAVIS=s
interpretation. BOR=s response to this argument is that this was a much
smaller order, the payments did not appear to be excessive, and the agency
simply elected not to devote resources to seeking repayment of any overpayments
that might have been made. BOR also
points out that once an appeal is taken, the Board may decide the appeal
without deference to the contracting officer=s
findings in her final decision. See
Wilner v. United States, 24 F.3d 1397, 1401 (Fed. Cir. 1994)(en
banc). Thus, the acceptance of the IT
invoices may still be revisited. We
agree with BOR that this argument does not require the conclusion that the task orders must be paid
using JAVIS=s T&M rates.
Upon consideration of the undisputed facts before us,
we find that BOR has demonstrated that as a matter of law the task orders
created CPFF contracts. BOR consistently
made it clear that it expected to reimburse JAVIS on a CPFF basis. JAVIS=s
interpretation would render the CPFF provisions in the task orders superfluous
and would effectuate the contractor=s
subjective intent.
Although we are persuaded that, as a matter of law,
BOR is entitled to prevail on the question of whether the proper billing rates
are CPFF or T&M, we are not convinced that the amount of the overpayment
alleged by BOR is sufficiently accurate that we should deny the appeal
outright. Although both parties seem to
expect that resolution of the question of whether the task orders were CPFF or
T&M will fully resolve the appeal, that is not the case. Neither party has provided sufficient support
for the dollars claimed to decide the amount in dispute given the record
available to the Board. Thus, while the
agency has prevailed as to the type of contract performed, it has not
demonstrated that the amount by which it considers JAVIS to have been overpaid is correct. Accordingly, we grant BOR=s motion limited to the question of the nature of the
contract and the corollary pricing of the services provided. The amount of the overpayment, if any, that
BOR may be entitled to collect back from the contractor remains to be
determined.
Decision
Respondent=s motion
for summary relief is GRANTED IN PART.
Appellant=s motion for summary relief is DENIED.
_________________________________
CATHERINE B. HYATT
Board Judge
We concur:
__________________________________ _________________________________
STEPHEN M.
DANIELS BERYL
S. GILMORE
Board Judge Board
Judge
[1] The
joint stipulation of facts filed by the parties is cited herein as SF
(stipulated fact) together with the numbered paragraph(s).
[2] The
GIS task order also included remote sensing (RS) services. Appeal File, Exhibit B.2.
[3] In a
memorandum to BOR, issued on November 16, 2005, DCAA advised that JAVIS had not
responded to repeated requests for the contractor=s
certified incurred costs proposal for JAVIS=s fiscal
year ending December 31, 2003. For that
reason DCAA recommended that the contracting officer unilaterally establish
contract costs set low enough to ensure that no potentially unallowable costs
would be reimbursed. DCAA=s rationale for this position is set forth in
pertinent part:
Recent relevant historical data is not available for
Javis . . . for fiscal year December 31, 2003.
Therefore, we recommend that you unilaterally determine contract costs
using a DCAA-wide decrement factor of 20 percent applied to contract costs
(direct and indirect) for FY 2003. . . .
The 20 percent decrement factor is based on DCAA-wide questioned costs
for high-risk contractors. Because Javis
. . . has not complied with FAR 52.216-7 and furnished the contracting officer
and DCAA its certified indirect cost rate proposal for fiscal year 2003, we
consider Javis . . . to be a high-risk contractor. We believe the 20 percent is conservative
because it is based on contractor costs after voluntary exclusions of
unallowable costs, and the 20 percent is applied to contractor costs as
identified in the books and records that probably do not exclude unallowable
costs.
Appeal File, Exhibit E.2.
[4] The
affidavit of Mr. Long, see Finding 31, does not establish that the BOR
contracting officer agreed to accept JAVIS=s
proposed T&M rates to price the GIS task order. The affidavit refers to a conversation with
the BOR contracting officer, the DCAA auditor and states that JAVIS Aunderstood@ that it
could bill the task order as a T&M contract. The only participant in that conversation
with authority to agree to this was the contracting officer, and there is no
documentation or other evidence that she ever did so, other than Mr. Long=s vague statement that JAVIS understood that it could
bill the task orders as T&M efforts.
This falls short of creating a material issue of fact.
There is also an e-mail message from a
DCAA auditor seeking clarification of why appellant provided T&M rates in
response to CPFF task orders. On the
following page there is a cryptic statement, with no identified author, to the
effect that after JAVIS explained its labor rates, the agency validated them
during the audit. Appeal File, Exhibit
C.2.15. This document is too vague and
questionable to suffice to create a genuine issue of fact. In any event, after some early confusion,
DCAA corrected its report to reflect that the task orders were CPFF
contracts.