|
|
DENIED:
February 9, 2009
CBCA 1110
B & M CILLESSEN CONSTRUCTION CO., INC.,
Appellant,
v.
DEPARTMENT OF HEALTH AND HUMAN SERVICES,
Respondent.
Seth
V. Bingham of Miller Stratvert P.A., Farmington, NM, counsel for Appellant.
Nigel
F. Gant, Office of the General Counsel, Department of Health and Human
Services, Dallas, TX, counsel for Respondent.
Before Board Judges HYATT,
DRUMMOND, and SHERIDAN.
SHERIDAN, Board Judge.
This appeal arises out of
contract HHSI161200700014C, for the renovation and construction of an expansion
to the Chinle Comprehensive Health Care Center (Chinle Center) in Chinle,
Arizona, which was awarded to B & M Cillessen Construction Co., Inc.
(Cillessen) by the Indian Health Service (IHS), Department of Health and Human
Services. Cillessen seeks $131,481 in
increased taxes. Based on the findings and
application of the law set forth below, we deny the appeal.
The appeal was submitted on
the written record pursuant to Board Rule 19.
The record considered by the Board in issuing this decision consists of
the pleadings, the appeal file (exhibits 1 through 44) , appellant=s Rule 19 submission; respondent=s Rule 19 submission, and appellant=s Rule 19 reply.
Background
On December 7, 2006, IHS
issued a notice that they would be
soliciting offers for the expansion and renovation of the Chinle
Center. Appeal File, Exhibit 1. The notice informed potential offerors that
IHS intended to award a firm fixed-price construction typ contract. Id.
Solicitation HHSI161200700014C was issued on January 11, 2007, informing
prospective offerors this was to be a negotiated procurement in which IHS was
using a Acompetitive formal best value source selection process@ in accordance with Federal Acquisition Regulation
(FAR) part 15 Ato ensure selection of the source evidencing the best
overall capability to perform the work in a manner most advantageous to the
Government, as determined by evaluation of proposals in accordance with the
established criteria.@ Id.,
Exhibit 5 at 1, 61.[1] The solicitation also notified prospective
offerors that IHS intended to award a firm fixed-price construction type
contract. Id. at 55.
Prospective offerors were
warned in section H-5 of the solicitation that, prior to submitting prices,
they should check with the Tribal Tax Office to determine the appropriate taxes
to include in their proposals:
The Tribal Organization within the area of this
contract may levy taxes. The contractor
must contact the Tribal Tax Office to determine the appropriate taxes to be
included in the proposed price.
Appeal File, Exhibit 5 at 29. Contractors were cautioned to inquire and
seek clarification concerning possible ambiguities in the solicitation. Id.
The solicitation also noted that several FAR clauses would be
incorporated by reference into the contract.
Among the clauses to be incorporated by reference was FAR 52.229-3. Id. at 36.[2]
FAR 52.229-3 Federal, State,
and Local Taxes (April 2006) provides, inter alia, that:
(a) As used in this clause‑‑
All applicable Federal, State, and local taxes and
duties, means all taxes and duties, in effect on the contract date, that the
taxing authority is imposing and collecting on the transactions or property
covered by this contract.
Contract date, means the date set for bid opening or,
if this is a negotiated contract or a modification, the effective date of this
contract or modification.
. . . .
(b) The contract price includes all applicable
Federal, State, and local taxes and duties.
48 CFR 52.229-3 (2006) (emphasis added).
Mr. William Obershaw, the
chief of the contracting office at IHS Division of Engineering Services in
Dallas, Texas, was the senior contracting officer responsible for administering
the Chinle Center project. Appeal File,
Exhibit 19. On February 1, 2007, a
pre-proposal conference was held to, among other things, Aimprove the understanding of Government requirements
and industry capabilities.@ Id.,
Exhibit 8. Written materials for the
conference informed prospective offerors that they Aha[d] a duty to inquire and seek clarification
concerning possible ambiguities and/or discrepancies.@ Id. at
7. Contractors were also warned that A[u]nless otherwise provided in this contract, the
contract price includes all applicable Federal, State, and local taxes and
duties.@ Id. at
16. Price proposals were to be submitted
in a separate sealed envelope, and were to include Athe cost of new materials, labor and equipment, as
well as taxes (State, Tribal and TERO [Tribal Employment Rights Office]),
insurance & bonds, overhead and profit.@ Id. at 28. Again, the potential offerors were told that
IHS Aintend[ed] to award a firm fixed-price construction
type contract to the responsive and responsible offeror whose proposal conforms
to the requirements of the solicitation and will provide the best value to the
Government.@ Id. at
29.
Believing that a tribal tax
would be levied on the construction associated with the Chinle Center, on
February 7, 2007, Ms. Rose Coburn, Cillessen=s
Corporate Secretary, contacted Ms. Mary Etsitty, the Executive Director of the
Navajo Tax Commission, to ask about taxes.
The Chinle Center is within the Navajo Nation, and Ms. Coburn was
informed that a Navajo Business Activities Tax (NBAT) was required to be paid
on the gross receipts received from the construction of the center. Appeal File, Exhibit 30; Complaint & 14. Ms.
Etsitty told Ms. Coburn that as of February 7 the applicable NBAT rate was
three percent. Appeal File, Exhibit
40. However, at that time she also told
Ms. Coburn that an increase to a four percent NBAT, to be effective July 1,
2007, was currently being considered. Id.; see also id., Exhibit 38.[3]
The pre-solicitation notice
was modified several times to extend the original deadline for proposals from
February 22 to March 14, 2007. Appeal
File, Exhibits 2-4. Cillessen submitted its
proposal for the Chinle Center project on March 14, 2007. Id., Exhibit 10.
On March 28, 2007, the Navajo
Tax Commission approved an increase in the NBAT, from three percent to four
percent, to be effective July 1, 2007.
Appeal File, Exhibit 25. A news
release to that effect was issued by the Navajo Nation on March 30, 2007. Id.
A source selection board was
appointed, and the members individually reviewed and ranked the five firms
which had submitted proposals on the Chinle Center project. Appeal File, Exhibits 13, 14. As Cillessen was rated as the most qualified
responsive and responsible offeror, and also had proposed a significantly lower
price for the project than the second most qualified firm, the selection board
elected to not conduct further negotiations with the offerors. Appeal File, Exhibit 14. They recommended award of the contract to
Cillessen. Id.
Cillessen was notified that it
was being considered for the award of the Chinle Center project on April 4,
2007, and asked to confirm its offer.
Appeal File, Exhibit 15. Cillessen
confirmed its offer that same day.
Appeal File, Exhibit 16. Via
letter dated April 10, 2007, Cillessen was informed that it was awarded
contract HHSI161200700014C, in the amount of $12,298,000, for the expansion and
renovation of the Chinle Center. Id.
Exhibit, 17. The Standard Form 33 shows
the effective date of award as April 11, 2007.
Id., Exhibit 18. A pre-construction conference was held on May
16, 2007, where the notice to proceed was issued and Cillessen was authorized
to begin work on May 17, 2007. Id.,
Exhibit 21. The project was required to
be completed within 459 calendar days, and a completion date was established as
August 17, 2008. Id.
On
July 27, 2007, Cillessen forwarded to the contracting officer a request for an
equitable adjustment (REA) seeking an increase of $131,481 to the contract
amount due to the increase in the NBAT.
Appeal File, Exhibit 24.
Cillessen informed the contracting officer that the one percent increase
applied to the gross receipts on the contract after July 1, 2007. Id.
Appellant=s Vice President, Mr. Jeffrey Cillessen, wrote Mr.
Obershaw on July 30, 2007, representing Awe were
unaware of the tax increase or potential increase at the time of our
proposal. Had we been aware we would
have asked for clarification prior to our submission of bid.@ Id., Exhibit 28.
Mr. Obershaw responded on July
30, 2007, denying an equitable adjustment for the NBAT increase. Appeal File, Exhibit 26. Further correspondence culminated in Mr.
Obershaw writing Cillessen on July 31, 2007, suggesting that if Cillessen was
still in disagreement with the Government=s
decision to deny the REA, it should proceed under the disputes procedures set
forth in FAR 52.233-1 (Alt. 1). Id.,
Exhibit 29. The claim was resubmitted
with proper certification, and on
February 21, 2008, the contracting officer issued a final decision denying the
claim. Id., Exhibits 36, 37.
Discussion
The issue before us is whether
appellant should be able to pass on to the Government a one percent Navajo
Nation tax increase that occurred after appellant had submitted its proposal,
but before the contract was awarded.
Appellant asserts that it
properly bid the project and is entitled to Aan
automatic increase@ or Aan equitable adjustment@ in the
contract price to cover a $131,481 increase in the NBAT. Appellant argues that FAR regulations support
an adjustment to the contract price.
Alternatively, appellant posits the contract price should be reformed
based on mutual or unilateral mistake.
Respondent replies that this
was a competitive procurement properly conducted pursuant to FAR 52.215-1 that
resulted in a firm fixed-price contract.
Respondent argues that appellant is not entitled to an equitable
adjustment to compensate it for the increase in the tax rate under the terms of
the contract, under applicable FAR provisions, or based on mistake.
In this fixed-price contract
the risk of applicable increased state, local, and tribal taxes fell on the
contractor. It is well‑settled
that in a firm fixed‑price contract, the contractor assumes the risk of
all increased costs except as specifically provided for in the contract. HLI Lordship Industries, Inc., VABCA
1785, 86‑3 BCA & 19,182, at 97,026 (1985) (citing ITT Arctic
Services, Inc. v. United States, 524 F.2d 680 (Ct. Cl. 1975); McNamara
Construction of Manitoba, Ltd. v. United States, 509 F.2d 1166 (Ct. Cl.
1975); Sperry Rand Corp. v. United States, 475 F.2d 1168 (Ct. Cl.
1973). FAR 52.229-3 clearly and
unequivocally places responsibility squarely on prospective contractors to
include all applicable taxes in their bids or proposals. Hunt Construction Corp. v. United States,
281 F.3d 1369, 1372-73 (Fed. Cir. 2002) (cited for authority in Robertson
& Penn, Inc., ASBCA 55622, 08-2 BCA &
33,921, at 167,859); see also Fields Roof Service, Inc., VABCA 3147,
90-3 BCA & 23,232.
FAR 52.229-3 was properly
incorporated by reference into the contract.[4] The clause specified that the Acontract price includes all applicable Federal, State,
and local taxes and duties.@ 48 CFR
52.229-3(b). AAll applicable Federal, State, and local taxes@ referred to Aall
taxes and duties, in effect on the contract date,@ with Acontract date@ defined
as Athe date set for bid opening or, if this is a
negotiated contract . . . the effective date of this contract.@ 48 CFR
52.229-3(a) (emphasis added).
Under FAR 52.229-3, a
contractor is responsible for making sure it includes the appropriate taxes in
its bid or proposal. Gibson Motor
& Machine Service, Inc., ASBCA 24363, 80‑1 BCA & 14,442, at 71,202 (Athe duty
of determining tax applicability is on the bidder@); see
also Turner Construction Co. v. General Services v. General Services
Administration, 92-3 BCA & 25, 115. To
fulfill this responsibility, prospective contractors are responsible for
conducting a sufficient investigation to ascertain the existence or
nonexistence of taxes. GarCom, Inc.,
ASBCA 55034, 06‑1 BCA & 33,146 (2005).
Based on the terms of the contract and the facts before us, appellant
assumed the risk for paying all taxes that were applicable to the contract as
of the contract=s effective date, which for this procurement was the
date of award, April 10, 2007. Appellant
may not pass on to the Government the consequences of its own failure to raise
the fact of the tax rate increase prior to award.[5]
Appellant also asserts it is
entitled the $131,481 increase because FAR 52.229-3(c) provides that Athe contract price shall be increased by the amount of
any after‑imposed Federal tax that was not included in the
contract price,@ provided certain conditions are met.[6] This argument fails for two reasons: the
increase was neither an after-imposed tax nor a federal tax. The tax rate increase was not after-imposed
since it was made known to the public on March 30, 2007. Also, FAR 52.229-3 has been consistently
interpreted to deny contractors recovery for after-imposed state, local, and
tribal taxes. Cannon Structures, Inc.,
IBCA 3968‑98, 99‑1 BCA &
30,236; Professional Services Unified, Inc., ASBCA 48883, 96‑1 BCA
& 28,073 (1995); Walker Equipment v. International
Boundary and Water Commission, GSBCA 11572‑IBWC, 93‑3 BCA & 25,954; MIDCON of New Mexico, Inc., ASBCA
37249, 90‑1 BCA & 22,621; Northwest Piping, Inc., IBCA 2611‑A,
89‑2 BCA & 21,794; Humphrey Construction, Inc., IBCA
2266, et al., 87‑2 BCA & 19,923.
We
also find no merit in appellant=s argument that the clause contained at FAR 52‑229‑4
should apply to this contract. FAR 52‑229‑4
may be used for noncompetitive contracts at the discretion of a contracting
officer. 48 CFR 29.401-3(b). Unlike FAR 52.229-3, which only provides
relief from after-imposed federal taxes, FAR 52‑229‑4 allows
contractors to recoup after‑imposed federal, state, and local taxes that
it is required to pay. 48 CFR
52.229-4. As we noted earlier, FAR
52.229-3 was the appropriate clause to use in this contract. Appellant has provided no facts or
justification to apply FAR 52.229‑4 to this contract.
Finally, appellant has
provided no compelling facts supporting its argument alleging unilateral or
mutual mistake. We conclude that any
failure on the part of appellant to ascertain the appropriate amount of NBAT
for which it was responsible under the contract was a mistake in judgment. When appellant elected not to raise the tax
increase with the Government prior to award it compounded its error in
judgment. Contractual relief is not
available for errors in judgment. Satyadev
Duggirala v. General Services Administration, CBCA 463, 07‑1 BCA & 33,489, at 165,999 (citing McClure Electrical
Constructors v. Dalton, 132 F.3d 709 (Fed. Cir. 1997)).
After considering the facts
and each of the arguments propounded by appellant, we are not persuaded that
the costs it incurred as a result of the NBAT rate increase should be passed on
to the Government.
Decision
The appeal is DENIED.
_____________________________
PATRICIA J. SHERIDAN
Board Judge
We concur:
CATHERINE B. HYATT JEROME
M. DRUMMOND
Board Judge Board
Judge
[1] Prospective
offerors were provided instructions on this procurement through FAR 52.215-1,
Instructions to Offerors-Competitive Acquisition (Jan. 2004), which was
incorporated by reference into the solicitation. Appeal File, Exhibit 5 at 55. In this type of competitive procurement, the
Government first ranks the responsible offerors. After a pool of qualified offerors is
determined, the Government considers the price proposals from that pool of
offerors. This type of competitive procurement is sometimes referred to as a Atwo-step procurement.@
[2] FAR 52.229-3
is required to be inserted in solicitations and contracts except A(b) In a noncompetitive contract . . . the contracting
officer may insert the clause at 52.229-4 Federal, State, and Local Taxes
(State and Local Adjustments), instead of the clause at 52.229‑3, if the
price would otherwise include an inappropriate contingency for potential
post-award changes(s) in State or local taxes.@ 49 CFR 29.401-3 (2003).
[3] In a letter
dated March 20, 2008, to Ms. Amy Alderman at the Navajo Tax Commission, Ms.
Coburn remembered her conversation with Ms. Etsitty as:
[Ms. Etsitty] stated [the tax increase from three to
four percent] had not been voted on as yet, but there could be a tax increase
to [four percent] if the tax commission did approve it. She also stated we would receive written
notification one to two months prior to the increase. When I asked about contracts that would be
existing, if and when the tax was increased, she stated there would have to be
provisions made [for the NBAT] to remain at the [three percent].
Appeal File, Exhibit 40.
[4] FAR 52.229-3
was required to be used in the contract pursuant to the prescription contained
at FAR 29.401-3(a).
[5] Here,
appellant began the process of ascertaining the applicable taxes, but its
investigation fell short. Being fully
aware it was responsible for paying the applicable NBAT, and that a rate
increase was under active consideration, appellant apparently failed to check
back to see whether there had been a rate increase or verify that the rate
increase would not apply to receipts from the contract. The tax rate was increased, and a press
release issued giving notice of the increase, prior to appellant confirming its
proposal. However, whether or not
appellant acted prudently when it failed to follow-up on the proposed increase
is not dispositive to this decision because under the terms of the contract
appellant still had the responsibility for paying the applicable taxes.
[6] To obtain
relief from after-imposed federal taxes, a contractor must warrant in
writing that Ano amount for such newly imposed Federal . . . tax . .
. or rate increase was included in the contract price, as a contingency reserve
or otherwise.@ 48 CFR
52.229-3(c).