|
|
October
28, 2008
CBCA
1166-RELO
In the Matter of VINCENT
A. LeDUC
Vincent A. LeDuc, Daphne, AL,
Claimant.
Anne Schmitt-Shoemaker, Deputy
Director, Finance Center, Army Corps of Engineers, Millington, TN, appearing
for Department of the Army.
POLLACK,
Board Judge.
Vincent LeDuc was billed
$3286.59 by the United States Army Corps of Engineers (Corps) for excess weight
of household goods (HHG) arising out of his move from Union, Kentucky, to
Mobile, Alabama. According to the Corps,
the HHG were initially weighed at 21,460 pounds, later re-weighed, and based
upon the re-weigh, reduced to 21,120 pounds.
Since the weight exceeded 18,000 pounds, Mr. LeDuc was charged for the
excess. Mr. LeDuc challenges the
accuracy of both the initial weight and the re-weigh, asserting that when he
had moved to Union, Kentucky, his HHG weighed well under 18,000 pounds and that
during his residency in Kentucky he disposed of items rather than accumulated
additional items. In support, he
provided weight tickets for the move to Kentucky in 2005, which showed the HHG
to be 15,600 pounds. More significantly,
Mr. LeDuc challenges the weights assigned to the goods on a separate, and we
find more convincing, basis. He
identifies significant discrepancies in the supporting data which the
Government has used to establish the claimed weight. Those discrepancies raise significant
questions as to the accuracy of the weight assigned by the carrier and accepted
by the Corps.
The HHG in question were not
immediately transferred from Mr. LeDuc=s
residence to his new station. Instead,
on August 29, 2007, the HHG were moved from his residence to a site in
Theodore, Alabama, where on September 4, 2007, they were placed into storage in
transit (SIT). It is unclear from the
record how or when the initial weight was assigned. Despite Board requests to the Corps, we have
been provided no backup data as to the initial assigned weight and less than
credible backup as to the re-weigh.
The initial HHG weight was
assigned at some point between pickup at Mr. LeDuc=s residence on August 29 and delivery to the SIT
facility on September 4, 2007. The bill
of lading provided by the Government shows that the goods were shipped to
Alabama on August 30 and arrived at the delivery site, the SIT facility, on
September 4. Block 20 of the form shows
Kessler Air Force Base (AFB) as the responsible Government entity and shows that
the carrier assigned a weight of 21,460 to the HHG. It is noteworthy that block 26 of the bill of
lading provides, AREWEIGH REQUIRED - BEFORE EFFECTING DELIVERY TO
RESIDENCE OR PLACING IN STORAGE, THE CARRIER SHALL NOTIFY THE PPSO SPECIFIED IN
BLOCK 20.@ As addressed
in more detail below, the HHG were not re-weighed at the time they were placed
into the SIT facility.
During the time frame that the
HHG were at the SIT facility, the carrier submitted two separate bills to the
Government, one dated October 15, 2007, and the other October 22, 2007. In most respects the bills were identical,
and each showed a weight of 21,460 pounds.
Apparently, due to uncertainty as to where to send the bill, one bill
was sent to Defense Finance and Accounting Service-Indianapolis Center and the
other to the Corps directly. Both bills
were signed by B Day, on behalf of the carrier.
What differs as to the bills is that the October 22 bill to the Corps
had two separate signatures for B Day, each written in different
handwriting. Additionally, nothing on
either bill reflected a weighing date or
how the assigned weight was reached.
At some time after the HHG
arrived at the SIT facility, Mr. LeDuc was advised of the assigned weight and
requested a re-weigh. The Corps does not
contest the timeliness of his request.
Accordingly, timeliness is not an issue.
The Corps and Mr. LeDuc agree
that the HHG were delivered to Mr. LeDuc=s residence in Mobile on November 12,
2007. It appears that the HHG were
picked up from the SIT facility on that same date. Mr. LeDuc says that two trucks were used for
the delivery. Neither the Government nor
the carrier has contested that point.
This is significant because the supporting data provided for the
re-weigh included weights from three, not two, trucks. The entry of weight for the third truck has
not been adequately explained.
After delivery, the Corps by
letter advised Mr. LeDuc of an overpayment, contending that the re-weigh was
21,120 pounds. Mr. LeDuc contested that
poundage and as a result, the Corps sought additional information from the
carrier, including weight tickets. The
company provided eight weight tickets.
The tickets, however, had discrepancies which required
clarification. Accordingly, a meeting
was held with officials of the relocation company at Kessler AFB on March 5,
2008, in order to clarify concerns raised by Mr. LeDuc. The relocation company addressed both the
weighing of items in the SIT facility and the specific weights assigned on the
re-weigh and further acknowledged that the
better practice would have been to weigh the HHG at the time they
arrived at the SIT facility (not done), a procedure not always followed by the
company. As to concerns over the
tickets, the carrier response was short on specifics, but essentially said that
even though there were problems with the tickets, the weight for which the
Government was charged was accurate because the weighing company said it was
accurate.
The verification for the
assigned weight consisted of eight weight tickets. Each showed that the HHG were weighed at the
same weighing facility. The first two
tickets each show a weight of 5180 pounds.
Each is dated November 12, 2007, the date of the move. However, each is signed by a separate
weighmaster. Further, the underlying
data as to gross weight of the vehicle, as well as the steer axle and drive
axle components, differ for each of these tickets even though the vehicle is
identified as the same. The next two
tickets each show a weight of 6200 pounds.
These two are dated November 15, 2007, three days after the move. That, of course, is impossible. Again, each ticket shows a different
weighmaster and, as with the first set of tickets, the gross weights and
components differ. There is no
explanation for how one gets to the gross weight of 6200. Those two tickets are then followed by
another set, which each show 3960 pounds.
Each shows the weigh date as November 16, 2007, four days after
delivery. Again the various component
weights on the two tickets differ and are not tied into the claimed weight. Finally, on the last set of tickets, which
shows 5780 pounds, again there are different weighmasters, but this time the
tickets reflect two different dates.
One carries a November 12 date,
while the other shows the weighing as of November 14. If we add the 5180, 6200, 3960, and 5780
pounds, we arrive at 21,120 pounds.
While we can arrive at the
Corps= total for HHG weight by combining the numbers on
selected tickets, for at least two of those weights we are given verification
dates that were well after the goods were already delivered to the
residence. In a third instance, we have
one ticket showing weighing on the delivery date, but another, with the
identical weight, showing the weighing as occurring on a date after delivery. Finally, it should be noted that the tickets
identify the use of three vehicles (with two sets showing the same
vehicle). That is of course problematic,
since only two trucks were used.
The carrier has responded to
the discrepancy in tickets by assuring the Corps that the weight provided was
completely accurate. That assurance,
however, was followed by the statement that although the carrier was sure the
weights were accurate, the official providing the assurance was unclear as to
why the dates were different. The
official continued, stating that, unfortunately, the operations manager at the
time of the LeDuc transaction was no longer with the company, so an answer to
the discrepancies was difficult to obtain.
The carrier said that it contacted the local CAT scale (weighing
station) to ask some questions concerning reprinting of tickets (alleged as a
possible explanation for the discrepancy in dates). The responding official then noted, AI was
not comfortable with the answer but was
told that they would try to find a copy of the original ticket and if
not they would try to reprint.@ He then said
that could explain the date difference, apparently referring to multiple dates
and different trucks.
Notwithstanding concerns with
the accuracy of the data, the agency has decided to take the carrier at its
word and presume the weight was accurate.
The agency so advised Mr. LeDuc, who then asked the Board to settle the
agency=s claim. In his
letter to the Board, he basically laid out many of the facts above.
In attempting to address the
case, the Board found the supporting data inconsistent and on its face
unreliable. Accordingly, by order dated
July 17, 2008, the Board, having what it considered inadequate information and
no road map tying various documents together, asked the parties to identify
specific documents relied upon to establish weight. We further asked the Corps
whether the re-weigh was done on the dates set out on the tickets, and if it
was done on a different date, to explain that.
The Corps was asked how it reconciled the November 12 delivery date with
later dates for weighing. It was also asked
how many trucks were used and whether any of the tickets were original weight
tickets.
The Corps responded in a
letter dated August 28, 2008. It
acknowledged that Mr. LeDuc had made a timely re-weigh request. It then explained that it does not arrange or
complete the receiving report for the receipt of services, and A[t]herefore, we are unable to support or dispute the
original weight or reweigh.@ It then noted
that Kessler AFB and the Blue Grass Army Depot, respectively, had arranged the
shipment and certified that the services were received as invoiced. Finally, it said that it was informed by an
official at Kessler, that Kessler was unable to verify the transaction at this
time due to the age of the transaction and lack of availability of documentation. The Corps then referenced an official of the
relocation company and repeated the relocation company position that the
tickets were accurate and that the discrepancy in the dates on the weight
tickets, versus the actual re-weigh, was due to the date on the ticket being
the print date and not the re-weigh date.
Discussion
In Charles E. Pixley,
GSBCA 16484-RELO, 05-1 BCA & 32,887, the board stated that under applicable
statute and regulation, the Government cannot pay for moving any more than
18,000 pounds of household goods and the employee whose goods are moved is
responsible for reimbursing the Government for the costs attributable to any
weight in excess of that figure. The
board further noted that the rules leave no room for compromise - if the
shipment exceeds 18,000 pounds, the employee must pay. See George W. Currie, GSBCA
15,199-RELO, 00-1 BCA & 30,814; Robert
K. Boggs, GSBCA 14948-RELO, 99-2 BCA &
30,491. The board continued, stating
that in the absence of proven error or fraud, the carrier=s weight is deemed to be accurate. Mere suspicion is not sufficient. Pixley, 05-1 BCA at 162,933-34.
Our predecessor, the General
Services Board of Contract Appeals (GSBCA), decided only three cases where it
found that an employee met the burden of proving the certified weights for the
movement of household goods was incorrect.
The last of those cases was Michael V. Torretta, GSBCA
16560-RELO, 05-1 BCA & 32,928. Torretta
is similar in many respects to Mr. LeDuc=s
appeal. In Torretta, the board
found serious discrepancies in data and inadequate Government explanations as
to the assigned weights. Here, the
discrepancies exceed those encountered in Torretta.
In Torretta, the agency
had furnished the claimant copies of weight tickets for three trucks, using
those tickets to justify the claimed weight.
In deciding the appeal, the board concluded that the weight tickets
relied upon by the Government could not themselves be relied upon, pointing out
that the tickets were for three trucks when only two were used and that a
claimed re-weigh presented other issues that made any reliance
unjustified. Here, the situation is even
more compelling. Not only does the data
relied upon reflect three trucks, when only two were used, but additionally,
the weight tickets provided are internally inconsistent and carry dates which
postdate the delivery of the goods.
In this appeal, the Government
was given multiple chances to provide information that had some
credibility. What it provided is neither
reliable nor credible. Mr. LeDuc is
being held to a weight that is based upon faulty data. Further, the agency has admitted it is
uncomfortable with the answers from the carrier and the carrier justifies its
position, asserting that it simply should be believed. The Government here has not only failed to
provide hard data, but the data it has provided raises questions as to how the
weights for the HHG were initially and subsequently assigned. If we had been provided reliable data, this
case would be resolved in favor of the Government, based on an underlying
presumption. However, the Government cannot rely on a presumption where the
data supporting its position raises serious issues as to accuracy and
reliability.
Mr. LeDuc believed the weight
was in error. He properly sought
relief. When a new number was provided,
he asked for verification. The
verification was unreliable. The choice
here is to find for the Government and rely on unreliable and unsupported
weight tickets, which do not even carry the right date, show a phantom truck,
and which even the relocation company and Corps are not comfortable endorsing,
or accept Mr. LeDuc=s contentions.
On balance, and admittedly this is a rare case, Mr. LeDuc=s evidence is far more convincing than that provided
by the Government and in our view shows that the Government number was arrived
at in error.
Accordingly, we find that Mr.
LeDuc has met the heavy burden of proving that the certified weights on which
the agency now appears to rely are clearly erroneous and the weight for the HHG
moved did not exceed 18,000 pounds. Mr.
LeDuc=s claim is therefore granted. The bill the agency sent him is invalid.
________________________________
HOWARD A. POLLACK
Board Judge